MARCH KEY FIGURES
| | Mar Qtr 12 | Dec Qtr 11 to Mar Qtr 12 | Mar Qtr 11 to Mar Qtr 12 |
| | $m | % change | % change |
|
Trend estimates(a) | | | |
| Total new capital expenditure | 40 067 | 4.3 | 28.3 |
| Buildings and structures | 24 149 | 6.4 | 45.3 |
| Equipment, plant and machinery | 15 798 | 0.3 | 8.2 |
Seasonally adjusted(a) | | | |
| Total new capital expenditure | 40 002 | 6.1 | 28.6 |
| Buildings and structures | 24 367 | 10.5 | 48.8 |
| Equipment, plant and machinery | 15 635 | -0.1 | 6.2 |
|
(a) In volume terms |
New Capital Expenditure, in Volume Terms
| |
MARCH KEY POINTS
ACTUAL EXPENDITURE (VOLUME TERMS)
- The trend volume estimate for total new capital expenditure rose 4.3% in the March quarter 2012 while the seasonally adjusted estimate rose 6.1%.
- The trend volume estimate for buildings and structures rose 6.4% in the March quarter 2012 while the seasonally adjusted estimate rose 10.5%.
- The trend volume estimate for equipment, plant and machinery rose 0.3% in the March quarter 2012 while the seasonally adjusted estimate fell 0.1%.
EXPECTED EXPENDITURE (CURRENT PRICE TERMS)
- This issue includes the sixth estimate (Estimate 6) for 2011-12 and the second estimate (Estimate 2) for 2012-13.
- Estimate 6 for 2011-12 is $158,028m. This is 27.5% higher than Estimate 6 for 2010-11. Estimate 6 is 2.3% lower than Estimate 5 for 2011-12.
- Estimate 2 for 2012-13 is $172,982m. This is 23.5% higher than Estimate 2 for 2011-12. Estimate 2 is 4.3% higher than Estimate 1 for 2012-13.
- See pages 6 to 9 for further commentary on expectations data.
NOTES
FORTHCOMING ISSUES
ISSUE (QUARTER) | Release Date |
June 2012 | 30 August 2012 |
September 2012 | 29 November 2012 |
December 2012 | 28 February 2013 |
March 2013 | 30 May 2013 |
FEATURE ARTICLE
A feature article titled 'Mining Investment in ABS Publications' begins on page 10.
INQUIRIES
For further information about these and related statistics, contact the National Information and Referral Service on 1300 135 070 or Liz Bolzan on Sydney (02) 9268 4508.